Proweps envirotec – with the Diefenbacher company as main contractor – was engaged in an innovative project to modernize and extend the existing anaerobic digestion plant of VafabMiljö in Västeras, Sweden. The complete 3D-engineering, project management and supervision of construction and commissioning was Proweps scope.
In the frame of the project, VafabMiljö modernised the existing 15 year old biogas plant and upgraded it with a second line. The capacity of the entire plant is expanded to 40,000 t of household waste, food waste and other liquid organic waste from restaurants, food production etc. The modern technology increased operational reliability and efficiency – especially the biogas yield between by 10 % – while methane losses and energy consumption are reduced. In a new additional gas upgrading plant, raw gas is also processed into vehicle gas with a total capacity of 2.7 million cubic meters.
The high quality liquid fermentation residues (digestate) produced for agriculture meet the requirements of the national Swedish SPCR120 quality assurance scheme. They are used and spread by farmers in the region as a liquide fertilizer.
Many new technical innovations are being implemented in the project. In addition it is a very good example how existing plants can be modernised. Therefore the project was co-financed by the Swedish Environmental Protection Agency through the “Klimatklivet” fund.
Two interesting videos below show a technical round tour and the public opening with statements of experts and politicians.
Contact us for further information: info@proweps-envirotec.com
After nearly 15 years of operation it was time for remodelling the VafabMiljö biogas plant in Västeras. The reconstruction and enlargement of the new plant was finished in 2021.
The new plant has the capacity for 40.000 tonnes of organic household and commercial waste annually which are converted into biogas and biofertilizers.
All of it aims to link together city and country in a cycle of nutrients and energy in the form of gas, to our city buses, and nutrient rich fertilizer for our farmers.
“It is obvious for the region that we need to focus on Climate issues because we see what is happening in the world with flooding and tornados even here in Sweden.
It is what Vafab does and so we never felt more right to open this type of new biogas facility which is now ready to process a lot of organic waste and food waste bags from households. It includes a new gas upgrading system which transforms biogas into gas which can be used as fuel for vehicles.
It is an important investment and the new plants works very well and thus makes us happy “remarks Carina Färm, Association Director of VafabMiljö.
Conversion from electricity to biomethane production The majority of biogas plants use biogas produced from…
The bioCNG plants have production capacities for 15 – 25 tons per day of bioCNG…
Recently, GPS Renewables took over 90 % of the business shares in proweps envirotec GmbH.
We have prepared the complete engineering for the biological waste treatment (anaerobic digestion and composting)…
Our longtime customer BRS Bioenergie GmbH has recently inaugurated his new biomethane production plant in…
The modernization works which included the design, engineering, supply and commissioning of a pretreatment and…